Ex-Steel Town

24. Juli 2009

Coke plant monessen

Founded in 1897 on the banks of the Monongahela river Monessen was named after its German role model  Essen, the famous industrial city at the Ruhr.

Once dominated by a 2 mile long buzzing strip of blast furnaces, rolling mills and steel works, employing 7000 people, Monessen became a remote ex-steel town by now.  About 60 percent of its once 20000 residents have left after  Wheeling-Pittsburgh Steel Corp. ceased production in 1986.

Mothballing the former Koppers coking plant ArcelorMittal will set free the last 116 steel workers in July.

 

ThyssenKrupp Steel, Duisburg

27. Juni 2009

Thyssenkrupp hochofen

Die August Thyssen Hütte wurde 1890 durch die Gewerkschaft Deutscher Kaiser als Siemens-Martin-Stahlwerk gegründet.
1895 werden Hochöfen, Thomas-Stahlwerk und eine Kokerei erbaut.1903 wurde der Werkshafen Schwelgern angelegt und 1928 die Großkokerei in Betrieb genommen. Wiederanblasen eines Hochofens nach Kriegszerstörung 1951. Inbetriebnahme des Oxygenstahlwerks 2 in Beekerwerth 1962. 1969 Stillegung der letzten Thomas- und Siemens-Martin-Stahlwerke.

Heute verfügt ThyssenKrupp Steel am Standort Duisburg über 5 Hochöfen (1,2,4,8,9) mit einer Kapazität von mehr als 30000 Tonnen Roheisen pro Tag. Die Stahlerzeugung erfolgt in zwei Qxygenstahlwerken mit 5 Konvertern (Schmelzgewichte: 265 und 380 Tonnen).2 Warmbreitbandstraßen, 1 Gießwalzanlage und 2 Kaltbandstraßen produzieren anschließend Bleche.

Stahlseite.

Siempelkamp giesst Weltrekord

29. Mai 2009

Giesserei Siempelkamp

Die Siempelkamp Giesserei in Krefeld arbeitet z.Z. an dem  bisher grössten  jemals produzierten Sphärogussteil und stellt damit ihren eigenen 10 Jahre alten Rekord ein. Der 252 Tonnen schwere Oberholm für eine Richtpresse der Dillinger Hütte wurde aus fünf Pfannen gegossen und wird noch etwa zwei Wochen abkühlen müssen. Bilder aus der Siempelkamp Giesserei auf der Stahlseite.

ArcelorMittal Eisenhüttenstadt nur noch mit einem Hochofen

21. Mai 2009

Hochofen Eisenhuettenstadt

In den kommenden sechs Monaten soll im ehemaligen EKO Stahlwerk in Eisenhüttenstadt nur noch der 1950 erbaute Hochofen 1 circa 1600 Tonnen Roheisen am Tag erzeugen. Der leistungsstärkere (4500 T/T) neue Hochofen 5a wird für diese  Zeit stillgesetzt.

Gustave Boëls Blast Furnaces

5. Mai 2009

in La Louviere, Belgium are gone for five years now.
The unique site included 6 furnaces. Two of them, built in 1912, were probably among the oldest remaining modern blast furnaces worldwide.
The image shows (ltr) furnaces 1-4 and No. 6, the largest and most advanced.
The remaining steel and rolling mills in La Louviere are now operated by the Swiss based Duferco group.
Further images from La Louviere at Stahlseite.

ArcelorMittal Burns Harbor

26. April 2009

ArcelorMittal Burns Harbor

Still one of the most advanced integrated mills in North America is the ArcelorMittal Burns Harbor site near Chicago.

Construction started in 1962 then still owned by the Bethlehem Steel company. In between 1969 and 1972 two blast furnaces, a coke plant (164 coke ovens) and a steel mill, containing two 300 ton BOF vessels were started.
In 1975 Bethlehem Steel’s first continuous slab caster started production. In 1978 a 110” plate mill and a third BOF vessel became operationalstyle. In 2000 the last ingots were poured. After filing bankruptcy Bethlehem Steel was taken over by the International Steel Group (ISG) in 2003. Two years later Burns Harbor became part of Mittal Steel USA (now ArcelorMittal). Further images at Stahlseite.

C. Grossmann Stahlguss

12. April 2009

The C. Grossmann Stahlguss GmbH in Solingen is the oldest working steel foundry in Germany. Founded in 1853 by Conrad Carl Grossmann it started producing steel clamps and keys.
Both open hearth furnaces installed in 1899 were replaced by Bessemer converters in 1918.

In 1956 the first electric arc furnace went into production and in 1984 an MRP converter was installed to improve steel quality.

Nowadays C. Grossmann manufactures steel castings up to 7 tons. Two electric arc furnace and a MRP converter produce up to 7 tons of liquid steel per tapping.

Further images at Stahlseite.

Giesserei Stahl, Solingen

 

 

Drahstrasse steht still

12. April 2009

drahtwalzwerk Duisburg

Wegen des dramatischen Umsatzeinbruchs bei Langprodukten wird ArcelorMittals Drahtstrasse in Hochfeld für mindestens drei Monate stillgelegt, die Beschäftigten gehen in 100% Kurzarbeit.

Das Oxygenstahlwerk in Duisburg Ruhrort soll ab dem 15.April wieder produzieren. Industriefotografie aus Duisburg auf der Stahlseite.

No more iron from the Meuse valley

10. April 2009

blast furnace liege

The ArcelorMittal steel company has announced to shut down its last blast furnace in the Liege bassin indefinitely. Blast furnace B in Ougree was  built in 1962,  hearth diameter is 9,75 meters. Blast furnace 6 in nearby Seraing is already down since late 2008. After there is no other hot metal supply in the Meuse valley the Chertal BOF shop and the hot strip mill will probably soon be closed too.

Further images at Stahlseite.

Hochofen Lüttich, Cockerill

 

 

No more steel from the Orne valley

1. April 2009

ArcelorMittal gandrange

128 years after German industrialist Karl Später founded the “Rombacher Hütte” the glow of steel making in Lorraine’s Orne valley is quenched. On March 31st, 2 pm world’s largest steel producer ArcelorMittal stopped  production at Gandrange’s 160 ton twin shell electric arc furnace.

According to ArcelorMittal  80 percent of the  571 steel workers  that were set free will find work at other ArcelorMittal plants nearby. Both rolling mills (bar and billet mill) are ment to continue their production. Thanks to Haiko for the hint.

Further images